Wandsworth drainage strategy and SuDS requirements
When a drainage design is needed, which runoff target to use and what Wandsworth planning conditions tend to ask for.
The short version
Wandsworth expects new development to use SuDS. A major application needs drainage and surface-water management designs. If an FRA is required, it should also show how the proposal follows the London drainage hierarchy.
- Major applications
- Drainage and surface-water designs
- Runoff objective
- Greenfield rate where technically feasible
- Fallback minimum
- At least 50% peak-rate attenuation
Use this as a starting point. Check the current validation list and the particular flood and drainage constraints on your site before submitting.
Start by confirming what the council asks for and which flood-risk tests apply to the site. Then use the document list and technical checks to set the scope. Further down, we look at the drainage conditions and refusal reasons found in the borough's decision notices.
When is a drainage strategy or FRA needed?
| Project situation | What to do | Status |
|---|---|---|
| Major development | Submit drainage and surface-water management designs for planning review. | Required |
| Development requiring an FRA | Use the FRA to demonstrate the London drainage hierarchy and the use of SuDS where feasible. | Required |
| Brownfield development above greenfield runoff | Show how far runoff has been reduced towards the greenfield rate and meet the policy fallback as a minimum. | Required |
| Site in a Critical Drainage Area or affected by mapped risk | Use the current SFRA and maps to define the assessment and design scope. | Check for this site |
| Infiltration or a sewer connection proposed | Provide the ground or connection evidence needed to show that the proposed discharge route is realistic. | Usually required |
What to send with the application
Prepare these first
- Drainage and surface-water management designs for major development
- Drainage-hierarchy assessment with runoff-rate and storage calculations
- Layout, levels, exceedance behaviour and the proposed discharge arrangement
- Site-specific adoption, access and maintenance arrangements
Add these if relevant
- Flood risk assessment where national, SFRA or site-specific triggers apply
- Ground and infiltration evidence where infiltration forms part of the strategy
- Connection evidence where discharge to a sewer or watercourse is proposed
- Flood-resilience or evacuation evidence where the risk assessment requires it
What the drawings and calculations need to show
Establish the planning and flood-risk trigger
Check the council's strategic flood risk assessment and current maps. The Lead Local Flood Authority will review a major proposal.
Follow the drainage hierarchy
Prioritise source-control SuDS and explain the ground conditions, infiltration potential and proposed discharge route.
Control runoff and size storage
Aim for greenfield runoff. Where that is not technically feasible, demonstrate how runoff has been minimised; the Local Plan sets a minimum 50% attenuation from the pre-development peak rate.
Design for climate change and operation
Use the current climate-change allowance, show exceedance behaviour and provide site-specific adoption and maintenance arrangements from the outset.
Major redevelopment of an existing hard-surfaced site
A brownfield site already drains quickly to the sewer and the initial layout leaves limited room for open SuDS.
- Test the drainage hierarchy and flood constraints before treating the existing sewer arrangement as the default.
- Aim for greenfield runoff; if that is demonstrably impracticable, show the maximum achievable reduction and at least the policy fallback.
- Coordinate attenuation storage, controls and exceedance with the levels and landscape design.
- State who will adopt, access, inspect and maintain the system throughout its design life.
This example shows how the submission might be assembled. It is not a drainage design. The final scope depends on the site and the proposal.
Official forms and guidance
- Wandsworth Council: managing development to reduce flood risk
- Wandsworth Council: adopted Local Plan
- Wandsworth Council: strategic flood risk assessment
- GLA: London Sustainable Drainage Proforma
- GOV.UK: when a flood risk assessment is required
- GOV.UK: national standards for sustainable drainage systems
These links were checked 3 September 2026. Forms and validation requirements do change, so check the council website again before issuing the application.
Observed planning-condition data
What the drainage conditions actually ask for
The theme breakdown appears once enough drainage-conditioned approvals have been read to report it reliably.
Allow for discharge before agreeing a start date
There are not yet enough records to publish a reliable borough figure. Check the exact wording on the permission before agreeing the programme.
- Copy the condition into a schedule and list the evidence that answers each clause.
- Check that the calculations, drawings, specifications and maintenance plan use the same assumptions and references.
- For a pre-commencement condition, secure the written discharge before starting any work covered by the restriction.
- Where the condition asks for verification, keep site photographs, installation records and as-built information.
Understand the programme effect of a pre-commencement condition .
Reasons drainage submissions are refused
We have not read enough refusals in Wandsworth to publish a useful local breakdown. The London-wide analysis is available for wider context.
Projects attracting these conditions
There are not yet enough records to publish a reliable project-type breakdown.
About the data
The observed figures are computed from the planning decision notices from Wandsworth and are recalculated as we read more. We do not publish a rate when its sample is too small. This is not a complete record of every decision made by the authority, and it cannot tell you whether a document will be accepted for a particular site. Only aggregate figures appear here. See the full methodology or the London-wide picture.